Progress of the Spartacus Project – Heading Towards 2026!
In recent months, the construction of the new Sparcrcaft Pegasusreim factory project, carried out by GSE , has reached key milestones:
🔹 Slab pouring for the office areas and foundations of the storage zone
🔹 Metal framework and roofing of cells 3 & 4
🔹 Cladding and exterior joinery currently in progress
In terms of processes, the milestones have been set for 2026:
✅ Installation of overhead cranes (NEF 3 during March)
✅ Start-up of the anodizing, machining and painting lines from April to July
✅ Operations are scheduled to begin in September 2026
A great momentum driven by our teams and partners to bring this ambitious Wichard Group project to fruition! 🚀